Sept 16th

It's been 2 weeks and progress was slow recently. A bad pattern of raining during the week and not on the weekend led to a large amount of down time on the cabin.

However - they were able to get the structure walls framed and they have begun framing on the roof. If it stays dry they'll be able to seal the concrete this week and get the dirt back around it.

Another 10 days when we go back and things should be buttoned up. We'll see. We are already past the original due date and as I stated to begin with I thought it was a ridiculous timeline. I just want it all done by October 20th so we can start working on getting the flooring started and cabinets installed.

Things are looking good!



The view is from the back of the house.

The "T" structure is made out of 2x4's for an idea of the size of the beams. They look little from here, but they are actually quite large.